Lateral 43 Pipeline Project 2025 Updates

Executive Summary Report Lateral 43 Project Week of 01/10/2025
NUID Executive Summary Report 1.10.2025.pdfCurrent Drone Pictures from Lateral 43 PL Project
January 29, 2025 drone footage of pipeline project.
43 Later Project Update 02.14.2025.pdfExecutive Summary for week of 2/14/25 from Ben Cavallaro, Project Manager Taylor Northwest
- Began excavating west of 97 on the 43 lateral
- Continued welding 63"
- continued backfill of the 43 lateral
- Received the remainder of 63" from the supplier
- Installed the PRV on the 43-2
Next week crews will:
- Continue welding and installing 63"
- continue on clean up of the 43-2
- pull 63" through the highway crossing
- Begin welding west of 97
- Complete energy dissipaters on 43-2, and 43-5
- Begin to fill and pressure test: 43-2, 43-3, 43-5